Progress to date
Projected and activity dates (latest date first) | |
Progress w/e 1 dec
|
|
*Second Site meeting 27 November with th profeesional. We discussed...
|
|
November progress , the timber work the preservations specialist and the electricals well under way now, and doing a great job. Select the document to see some pictures, I was strcuk on the light shining incrudible brightly in the Garnet chapel this after noon providing light of many colours- a blessing. A power surge has cause a few problem, firstly the heating control isn't working now, dress warmily. Secondly the photocopier couldn't cope with the power surge. We will endeavour to get these sorted asap. |
|
*Late October opening up the roof space - click to see the various pictures>>>>> | |
*24 October Work on the south side roof and guttering begins | |
*24 October - Scaffolding complete |
|
*23 October The organ sealed and protected from dust | |
*21 October internal scaffolding erected | |
*w/b 23rd October - lead work begins (phase 1) and will take 4-6 weeks | |
*w/b 16th October - organ protection. (Even though the work will be outside at this stage, dust will come in) | |
*9th October - 8am - scaffolding south side erected outside (phase 1). | |
*Start date Agreed 9 October | |
September 2017 Awaiting start date from our contractors. |
.