HLF Building progress

Progress to date

Projected and activity dates (latest date first)  

*November -Internal preservation work begins

 

*November - Electrical/lighting works begin 

 
*Late October opening up the roof space - click to see the various pictures>>>>>

*24 October Work on the south side roof and guttering begins

*24 October - Scaffolding complete

*23 October The organ sealed and protected from dust
*21 October internal scaffolding erected Image may contain: indoor
*w/b 23rd October - lead work begins (phase 1) and will take 4-6 weeks  
*w/b 16th October - organ protection. (Even though the work will be outside at this stage, dust will come in)  
*9th October - 8am - scaffolding south side erected outside (phase 1).
*Start date Agreed 9 October  
September 2017 Awaiting start date from our contractors.