Projected and activity dates (latest date first) |
|
Progress w/e 1 dec
- Work on the choir/vicars vestry begun, see pictures on the right hand side.
- Work on timer unit for heating and replacment photocopier started.
- Exterior lighting planned and begun, the interiour electrical work continued.
- The Creesington Park door refitted into a bespoke wooden frame.
- The project activities contur apace
|
|
*Second Site meeting 27 November with th profeesional. We discussed...
- Powersurge
- Electrics & lighting
- Two extra area of dry rot discovered
- Progress on schedule
- Christmas Break
|
|
November progress , the timber work the preservations specialist and the electricals well under way now, and doing a great job.
Select the document to see some pictures, I was strcuk on the light shining incrudible brightly in the Garnet chapel this after noon providing light of many colours- a blessing.
A power surge has cause a few problem, firstly the heating control isn't working now, dress warmily. Secondly the photocopier couldn't cope with the power surge. We will endeavour to get these sorted asap.
|
|
*Late October opening up the roof space - click to see the various pictures>>>>> |

|
*24 October Work on the south side roof and guttering begins |
 |
*24 October - Scaffolding complete
|
 |
*23 October The organ sealed and protected from dust |
 |
*21 October internal scaffolding erected |
 |
*w/b 23rd October - lead work begins (phase 1) and will take 4-6 weeks |
|
*w/b 16th October - organ protection. (Even though the work will be outside at this stage, dust will come in) |
|
*9th October - 8am - scaffolding south side erected outside (phase 1). |
 |
*Start date Agreed 9 October |
|
September 2017 Awaiting start date from our contractors. |
|